The decision of the Authority follows:
14 FLRA No. 101
NATIONAL FEDERATION OF FEDERAL
EMPLOYEES, LOCAL 1263
Union
and
DEFENSE LANGUAGE INSTITUTE,
PRESIDIO OF MONTEREY, CALIFORNIA
Agency
Case No. O-NG-745
DECISION AND ORDER ON NEGOTIABILITY ISSUES
The petition for review in this case comes before the Authority
pursuant to section 7105(a)(2)(E) of the Federal Service
Labor-Management Relations Statute (the Statute) and presents issues
concerning the negotiability of three provisions of a negotiated
agreement disapproved by the Agency pursuant to section 7114(c) of the
Statute. /1/ Upon careful consideration of the entire record, including
the parties' contentions, the Authority makes the following
determinations. /2/
Union Provision 1
Article 30, Section 2:
When the decision is to proceed with a proposal, the Employer
will continually apprise the Union of the status of the proposal.
The Union will be furnished a copy of each specification and
contract at the same time invitations for bids are mailed to
bidders. Also, the Union shall be furnished dates and times of
pre-bid and bid opening conferences and shall have the right to
have a union representative present at the conferences. (Only the
underscored portion is in dispute.)
The Agency contends that Union Provision 1 is substantially identical
to Union Proposal 3 which was found to be nonnegotiable in National
Federation of Federal Employees, Local 1167 and Department of the Air
Force, Headquarters, 31st Combat Support Group (TAC), Homestead Air
Force Base, Florida, 6 FLRA 574 (1981), affirmed sub nom. National
Federation of Federal Employees v. Federal Labor Relations Authority,
681 F.2d 886 (D.C. Cir. 1982). That proposal, like the one at issue in
the present case, required the union to be notified of certain pre-bid
and bid opening conferences and be permitted to have representatives at
such conferences. Based on the record before it in that case the
Authority found the proposal to be inconsistent with management's right
pursuant to section 7106(a)(2)(B) of the Statute "to make determinations
with respect to contracting out." Specifically, the Authority relied
upon the agency's uncontroverted claim that the pre-bid and bid opening
conferences referred to in the union's proposal were "wholly management
related meetings at which the management aspects of the contracting out
issue are either discussed or acted on." Thus, the Authority concluded,
in that case, such involvement of the exclusive representative in those
sessions where agency officials are engaged in management deliberation
and discussion as part of their decision-making process would directly
interfere with management's right to make determinations with respect to
contracting out.
However, based on the record in the present case we must reach a
different result. That is, the record in this case indicates that the
pre-bid and bid opening conferences involved in Union Provision 1 are
not wholly management related meetings, but are informal meetings open
to any member of the general public who wants to gather information
about the bidding process and the contract in question. The record does
not establish that allowing the Union an opportunity to be present at
these informational meetings which are open to the general public (as
contrasted with the "wholly management related meetings" at issue in the
Homestead Air Force Base case) will interfere with management's right
pursuant to the Statute to make determinations with respect to
contracting out. Therefore, as the Agency has not established that
Provision 1 would interfere with management's rights under the Statute,
it is within the Agency's obligation to bargain. /3/
Union Provision 2
Article 30, Section 2D:
Subsequent to opening of the bid and before a contract is
awarded, the Union shall be provided all data concerning the
"in-house" estimate of cost of the work to be performed. The
Union will be given ten (10) workdays, which may be extended upon
request, to review the "in-house" estimate and other pertinent
data and to comment on and/or challenge the validity of the data.
"All data will be corrected where the Union demonstrates that it
is not valid or prepared in accordance with existing directives."
(Only the underscored portion is in dispute.)
In agreement with the Union, the Authority finds that Union Provision
2 is not inconsistent either with management's right pursuant to section
7106(a)(2)(B) of the Statute "to make determinations with respect to
contracting out" or with OMB Circular A-76 as claimed by the Agency.
This provision would not establish, either expressly or by
incorporation, any particular limitation on management's right to make
contracting out determinations. Rather, the provision only would
provide a contractual procedure to assure that the data upon which a
contracting out determination will be based is valid and prepared in
accordance with existing external limitations on management's right,
including OMB Circular A-76. Thus, this provision is not inconsistent
with section 7106(a)(2)(B) of the Statute. See American Federation of
Government Employees, AFL-CIO, National Council of EEO Locals and Equal
Employment Opportunity Commission, 10 FLRA No. 1 (1982) (Union Proposal
1), appeal docketed, No. 82-2310 (D.C. Cir. Nov. 1, 1982).
Further, this provision is not concerned with the administrative
appeal procedure established by OMB Circular A-76 whereby all directly
affected parties to a contracting out determination, including Federal
employees and their unions, bidders and offerors, may appeal cost
comparison decisions. Instead, the record indicates that this provision
is intended to establish a separate procedure, preliminary to the OMB
Circular A-76 appeal procedure, for the Union, on behalf of employees
who would be adversely affected by a decision to contract out, to
challenge the cost data upon which the contracting out determination
will be based. After completion of the negotiated procedure, the Union,
as well as any directly affected 