Office of Administrative Law Judges
WASHINGTON, D.C.
U.S. DEPARTMENT OF COMMERCE PATENT AND TRADEMARK OFFICE
Respondent and PATENT OFFICE PROFESSIONAL ASSOCIATION Charging Party and GENERAL SERVICES ADMINISTRATION
|
Case No. WA-CA-70150 |
Christopher M. Feldenzer, Esquire For the General Counsel
Pamela R. Schwartz, Esquire For the Charging Party
Sharon J. Pomeranz, Esquire For the Intervenor
Marilyn Blandford, Esquire Robert L. Woods, Esquire For the Respondent
Before: JESSE ETELSON Administrative Law Judge
The Regional Director of the Federal Labor Relations Authority
(the Authority) for the Washington Regional Office issued an unfair
labor practice complaint alleging that Respondent (PTO) violated
sections 7116(a)(1) and (5) of the Federal Service Labor-Management
Relations Statute (the Statute). More specifically, the complaint
alleges that PTO violated sections 7116(a)(1) and (5) when
Intervenor (GSA), allegedly as PTO's agent, issued a Solicitation
for Offers (SFO) containing PTO's requirements for a consolidated
headquarters facility without providing the Charging Party (POPA or
the Union) with an opportunity to negotiate to the extent required
by the Statute.
PTO's answer denies that it issued the SFO or had authority to
do so, asserting that GSA issued the SFO pursuant to authority
granted exclusively to GSA. The answer also denies that the
specifications in the SFO were dictated by PTO and denies that it
committed the alleged unfair labor practice. PTO also asserts as a
defense, among others, that it had a good faith belief that it had
no duty to provide the Union with an opportunity to negotiate
because, at the time the SFO was issued, PTO had not made a final
decision to relocate to a new facility.
PTO and GSA filed motions for summary judgment dismissing the
complaint. At a prehearing conference, Judge Eli Nash, Jr.,
established April 3, 1998, as the date for submitting responses to
PTO's motion for summary judgment. On April 1, 1998, Chief Judge
Chaitovitz extended the time for responses to the motion to April
16. The Chief Judge assigned the case to me for a ruling on the
motion. The General Counsel and POPA submitted responses. For the
following reasons, I shall recommend that the Authority grant PTO's
motion for summary judgment.
Motions for summary judgment filed with Administrative Law
Judges serve the same purpose and have the same requirements as
motions for summary judgment filed with United States District
Courts pursuant to Rule 56 of the Federal Rules of Civil Procedure.
Department of Veterans Affairs, Veterans Affairs Medical
Center, Nashville, Tennessee, 50 FLRA 220, 222 (1995).(1) The standard for granting such motions
under Rule 56 is the absence of a genuine issue as to any material
fact and that the moving party is entitled to judgment as a matter
of law. "As to materiality, the substantive law will identify which
facts are material. Only disputes over facts that might affect the
outcome of the suit under the governing law will properly preclude
the entry of summary judgment. Factual disputes that are irrelevant
or unnecessary will not be counted." Anderson v. Liberty Lobby,
Inc., 477 U.S. 242, 248 (1986).
Although some of the statements set forth as facts in PTO's
motion for summary judgment are disputed, the following, which I
find sufficient on which to rule on the motion, are undisputed.
PTO currently occupies space in 16 locations in Crystal City,
Virginia, under 31 leases placed by GSA, the leasing agent for
Federal executive agencies, with the Charles E. Smith Companies and
Westfield Realty. The majority of PTO's leases had 1996
expirations.
Pursuant to the Public Buildings Act of 1959 (as amended), GSA
is required to submit project prospectuses to Congress, through the
Office of Management and Budget (OMB), for major leases exceeding
$1,810,000 average annual rental. Replacement space for PTO,
whether acquired by construction or lease, would require such
Congressional approval.
In 1989, PTO began working with GSA on alternative approaches
to meet PTO's long-range space requirements. In 1990, GSA
contracted with Leo A. Daly, an architectural- engineering firm, to
develop a "prospectus development study." Such a study was issued
in March 199l. It concluded that direct Federal construction was
the best approach to finding replacement space for PTO.
GSA contracted with Leo A. Daly for a space requirements
report. That report, a six-volume study produced in 1991-92,
identified PTO's long-term space needs. An early version of the
report was submitted to OMB in 1991 and was ultimately rejected.
GSA submitted further draft prospectuses in 1992, 1994, and January
1995. All were rejected for various reasons.
In April 1995, GSA submitted an "operating lease prospectus" to
OMB. OMB approved the prospectus in August 1995 and authorized GSA
to transmit it to the House and Senate Public Works Committees to
obtain authorization to acquire a competitively procured 20-year
operating lease for 1,989,116 occupiable square feet on a
consolidated site within an area in Northern Virginia lying between
the Potomac River and Dulles Airport. The prospectus set forth the
procurement method that GSA planned to use:
To achieve the prime objective of selecting the most
advantageous offer, a Source Selection process will
be used. The process will involve an impartial and
comprehensive evaluation of all proposals in order
to identify the one which achieves optimum
satisfaction of PTO's overall space objectives. A
high priority will be given to such evaluation
factors as price, site, quality and functionality of
buildings, including maintenance, availability of
public transportation,including Metrorail, parking,
and minimization of relocation costs.
The Senate and House Committees approved the prospectus in
October and November 1995, respectively, with directions to amend
the Source Selection process as follows:
"Provided, That any evaluation used for such
acquisition
considers proximity to public transportation, including
Metro Rail, to be a factor as important as any other
noncost factor."
On June 26, 1996, GSA issued SFO No. 96.004 for a PTO
consolidated headquarters facility. The SFO is an inch-thick
document, including nine amendments issued through 1997. It is in
the nature of a prospectus seeking proposals to provide PTO the
space it needs to house, on a long-term basis, its consolidated
headquarters facility. The SFO contains specifications for such
matters as occupiable square footage, "Class A condition," certain
defined amenities, a 20-year lease term with purchase options,
parking availability, and shuttle-bus service on any site farther
than 2,500 "walkable linear feet" from a Metrorail station. The SFO
describes an approach to the development of the site in stages and
states that a lease award is anticipated in the summer of 1998,
followed in four years by completion of the first of two blocks of
space to be made available. It also describes the procurement
procedures, including the preliminary and final submissions of
offers and the subsequent negotiation, evaluation, and selection
process. Only at the time of the lease award would the Government
(GSA and PTO) present a comprehensive Program of Requirements (POR)
for interior architecture, "which defines qualitative and
quantitative data, personnel, space, equipment, and functional
requirements" (R Ex. 7 at Section D pp. 2-3).
On the same day the SFO was issued, PTO Commissioner Bruce A.
Lehman issued a memorandum to all employees summarizing the status
of the procurement process and the steps remaining.
In September 1997, PTO awarded a contract to Deva and
Associates to undertake an analysis of the consolidation move
versus retention of the present PTO sites. The results of this
analysis were due in April 1998. In March 1998, the Department of
Commerce, PTO's parent agency, awarded a contract to Jefferson
Solutions to conduct a review of the PTO space project for the
purpose of validating the soundness of the project in defining,
among other things, the need for new space. The contract was
awarded in response to a December 1997 draft report from the
Department's Office of Inspector General that, while concluding
that PTO would benefit from a new facility, recommended further
assessment of the "space planning and build-out risks." A final
written report by Jefferson Solutions was due by April 14,
1998.
A. Contentions of the
Parties
The evidentiary facts concerning the status of PTO's decision
to relocate are undisputed. From these facts, POPA argues that, at
the time GSA issued the SFO, PTO had made a final decision to
relocate, while the General Counsel, in agreement with PTO in this
respect, concedes that PTO had not made a final decision. The
General Counsel also disagrees with PTO and POPA about the scope
and meaning of the Authority's decision in U.S. Department of
Health and Human Services, Social Security Administration, Region
I, Boston, Massachusetts, 47 FLRA 322 (1993)(SSA Region
I), which PTO and POPA read as holding that there is no duty
to bargain until a "final decision" to relocate has been made. The
General Counsel argues, however, that in the circumstances of this
case PTO was obligated to negotiate with POPA over the anticipated
relocation before GSA issued the SFO.
B. PTO Had Not Made a Final Decision
to Relocate
I infer from the undisputed facts that no final decision to
relocate had been made when GSA issued the SFO. A final decision
must be distinguished from a tentative decision or an expressed
intention to relocate such as is evidenced by Commissioner Lehman's
June 26, 1996, memorandum to all PTO employees (CP Ex. 3). For
notwithstanding an agency's unequivocal desire or intention to
relocate, a decision cannot be considered final until all matters
essential to making a final commitment to the move have been dealt
with. See my analysis as the Administrative Law Judge in
SSA Region I, 47 FLRA at 330-31.
Here, the steps taken in contemplation of a move had been
initiated but were far from complete. As Commissioner Lehman's June
1996 memorandum stated, the second phase of the "source selection
approach" begun in 1996 were expected to get underway in 1997. Even
then, offerors of facilities would submit only preliminary designs
and models, which would then be evaluated before negotiations with
five finalists among the offerers began. I believe that Counsel for
PTO accurately characterizes the SFO as a market survey from which
to identify potential sites.
While I shall discuss below the relationship between a "final
decision" to relocate and a final site selection, it is sufficient
at this point to note that, taking into consideration the total
process required before a final commitment to move could be made,
the situation in mid-1996 cannot be fairly characterized as one in
which a final decision had been reached. Further evidence of the
tentativeness of the decision (and for this purpose I believe it is
permissible to use the benefit of hindsight) may be found in the
reviews of the procurement process that have continued for almost
two years since the SFO was issued.
If the process were viewed as a walk through a forest, which it
does seem to resemble in some respects, the most that can be said
for PTO's progress in mid-1996 is that it had proceeded beyond some
of the trees. The clearing at the far end was not yet in sight,
even assuming that the map showed that it ought to be just ahead.
In short, PTO was not yet in a position to make a final decision to
relocate. It only hoped to be in that position as soon as possible.
That, however, is not the same thing.
C. There Was No Duty to
Bargain
The General Counsel, while conceding that no final decision to
relocate had been made (a concession that does not, of course, bind
POPA), argues that this is not dispositive of PTO's bargaining
obligation because, among other things, PTO should be found to have
had an obligation to bargain over the substance of at
least certain aspects of the decision to relocate. As the General
Counsel puts it, Authority precedent does not preclude such a
finding because, "[h]istorically, the Authority has confined its
analysis of the bargaining obligation under the Statute for office
relocations to matters of 'impact and implementation'" (Br. at
5).(2)
As I see it, however, the reason that, "historically," the
Authority has focused on impact and implementation (I&I)
bargaining is that it has long been understood that only such
bargaining, and not "substance" bargaining, is mandated.
Department of the Treasury, Internal Revenue Service, Midwest
Regional Office, Chicago, Illinois, 16 FLRA 141, 161 (1984)
(IRS Midwest).(3) See
also U.S. Department of Health and Human Services, Social Security
Administration, Baltimore, Maryland, 41 FLRA 339, 350
(1991)(relocating an office gives rise to an obligation to bargain
about I&I); Social Security Administration, Office of
Hearings and Appeals, Region II, New York, New York, 19 FLRA
328 (1985)(agency violated its duty to bargain when it exercised
its management right to relocate its office without negotiating
over the I&I of that exercise, where the relocation caused
changes in conditions of employment of unit employees that were
more than de minimis.)
The General Counsel acknowledges that, in SSA Region
I, the Authority upheld the Administrative Law Judge's
dismissal of a complaint alleging that the agency had violated the
Statute by refusing to bargain over the I&I of a contemplated
relocation. However, the General Counsel argues that the
Authority's affirmance of the Judge's dismissal was premised on the
limitation of the complaint to the refusal to bargain over I&I,
thereby distinguishing SSA Region I from the instant case,
where the complaint alleges that PTO failed to provide the Union
with an opportunity to negotiate "to the extent required by the
Statute."
Although the language of the complaint in this case
distinguishes it from the complaint in SSA Region I, that
distinction can be meaningful for our purposes only to the extent
that there are grounds for attributing to the Authority an
intention to expand the underlying bargaining obligation beyond
matters of I&I. The General Counsel suggests that the Authority
signaled its openness on this issue in footnote 4 of its SSA
Region I decision:
The complaint alleges only that the Union requested, and
the Respondent refused, to bargain over the impact and
implementation of the relocation of the Hyannis office. We
have found that no final decision to relocate the Hyannis
office had been made at the time of the Union's request and,
thus, no duty to bargain existed. Therefore, we do not need
to decide issues regarding the scope of the obligation to
bargain on matters related to such a final decision,
including the issue of where the office will relocate. (47
FLRA at 324).
PTO contends that this footnote means only that the Authority concluded that a duty to bargain must be established before the scope of that bargaining can be determined (Br. at 19-20).
I find it unnecessary to decide whether the Authority intended
to indicate there that it might be willing to consider expanding
the scope of bargaining in a case where the complaint is not
limited to an allegation of refusal to bargain over I&I. The
Authority has not yet gone so far as to actually reconsider its
precedent in this regard, and while it is privileged to do so, I am
not. At most, I have found it proper in certain circumstances to
exhort the Authority to reconsider doctrines that appear to me to
have unintended consequences, or, in rare instances, where other
factors seem to dictate rethinking of an issue.(4)
Notwithstanding footnote 4, the Authority clearly adopted the Judge's conclusion that the obligation to bargain (whatever its scope) arises only when a final decision to relocate has been made. The Authority's footnote 4 reaffirms that conclusion but suggests the possibility that in certain circumstances the issue of where the office will relocate might be negotiable. That suggestion, standing alone, might appear at first blush to be inconsistent with the principle that a bargaining obligation arises only after a final decision to relocate. But the apparent inconsistency is fact-dependent and does not affect the validity of the principle. A final decision to move could be made, at least theoretically (although this does not appear to be the case here), before the new site has been selected. In such a case, it would at least be possible to bargain over the new location after a final decision to move has been made, and the Authority could, consistent with its holding in SSA Region I, conclude that the issue of where the office will relocate is negotiable. Such a conclusion would be illusory, of course, where the decision to move is inextricably bound with the site selection.(5)
Having found, based on the undisputed material facts, that PTO
had not made a final decision to relocate at the time it is alleged
to have refused to bargain, and having concluded that, under
existing Authority precedent, such a final decision is a
prerequisite to any bargaining obligation concerning the
relocation, I conclude that there is no genuine issue as to any
material fact and that PTO is entitled to judgment as a matter of
law. Accordingly, I recommend that the Authority issue the
following order.(6)
Respondent U.S. Patent and Trademark Office's motion for
summary judgment is granted and the complaint is dismissed.(7)
Issued, Washington, DC, April 29, 1998.
____________________________
JESSE ETELSON
Administrative Law Judge
1. Section 2423.19 of the Authority's regulations, pursuant to which motions for summary judgment were filed until recently, no longer exists. However, under the Authority's July 31, 1997, amendments to its regulations concerning unfair labor practice proceedings, motions for summary judgment are submitted to Administrative Law Judges pursuant to section 2423.27. The standards for ruling on such motions have not been changed.
2. POPA also argues that a decision to relocate is not a management right.
3. Although the complaint in IRS Midwest alleged only a refusal to negotiate on the I&I of the decision to relocate, the union had not so limited its request to negotiate. Rather, it requested the right to negotiate the substance of the decision as well. IRS Midwest, 16 FLRA at 154.
4. - " " " " "" ' " " ' '